Current Projects

Look here to find information on current projects happening in our community to enhance your water service. 

"Subscribe" and receive updates on our Current Projects the minute they are posted.  It's easy!  Just click "Subscribe" - Located on the right hand side of this website.

East Lake Booster Pump Station

We are pleased to annouce we are building a new booster pump station northeast of Lake Fort Phantom. This project will include a 15,000 gallon ground storage tank, 1,500 gallon hydro-pneumatic tank, pump building that will have a triplex motor pump skid inside and generator. This project will ensure less interruptions in service in the event our supplier shuts the water off due to leaks. 

Capital Improvement Project 4 & 5

The project will begin at the intersection of FM 2404 and CR 499 (Summerhill Road). Work will be installing approximately 12,680 linear feet of 4-inch PVC waterline, 11,860 linear feet of 3-inch waterline along with bores and valves.

Capital Improvement Projects 2 & 3

From the Hawley Water Supply Corporation’s Booster Pump Station located on CR 376 outside of the city limits of Anson. Work will include installation of approximately 12,474 linear feet of 10-inch C-900, 12,397 linear feet of 8-inch C-900 and bores under HWY 277 along with valves and numerous fittings to FM 3326 (Egg Farm Road).

Currently in progress.

Capital Improvement Project - 6

Installation of approximately 11,651 LF of new 10" C900 PVC water line via open cut in place of existing 6" AC waterline. Existing 6" AC water line to be removed and legally disposed of. Project is located parallel and within US 83 ROW south of Hawley, TX. This section is part of the overall CIP 6 project and constitutes.

THIS PROJECT IS COMPLETED January 19, 2023